NEPRA has revised the base tariff rate for the consumer of IESCO company w.e.f 25/07/2022. So here is the list of complete tariff guide with new slab rates. Now you can calculate the iesco bill, all other wapda company bill with the help of this new updated guide. In this guide all tariff included like domestic, shop, agricultural, industrial, street light, temporary connection, bulk supply, railway station, housing society and all about you want to know. Just visit the iescobill.net for all kind of information.
A-1 GENERAL SUPPLY TARIFF – RESIDENTIAL | ||||||
Sr. No. | TARIFF CATEGORY / PARTICULARS | FIXED CHARGES Rs/kW/M | APPLICABLE VARIABLE CHARGES Rs./kWh | |||
a) | For Sanctioned load up to 5 kW | – | – | – | ||
Protected | ||||||
i | Up to 50 Units – Life Line | – | – | 3.95 | ||
ii | 01 – 100 Units – Life Line | – | – | 7.74 | ||
iii | 001 – 100 Units | – | – | 7.74 | ||
iv | 101 – 200 Units | – | – | 10.06 | ||
Un-Protected | ||||||
v | 1- 100 Units | – | – | 13.48 | ||
vi | 101- 200 Units | – | – | 18.58 | ||
vii | 201- 300 Units | – | – | 21.47 | ||
viii | 301- 400 Units | – | – | 24.63 | ||
ix | 401 – 500 Units | – | – | 26.09 | ||
x | 501 – 600 Units | – | – | 27.01 | ||
xi | 601 – 700 Units | – | – | 27.65 | ||
xii | Above 700 Units | – | – | 31.12 | ||
b) | For Sanctioned load 5 kW & above | – | – | – | ||
Peak | Off-Peak | |||||
Time Of Use | – | 33.23 | 26.91 | |||
As per the Authority’s decision only protected residential consumers will be given the benifits of one previous slab. | ||||||
As per Authority decision, residestial Life Line consumer will not be given any slab benefit. | ||||||
Under tariff A-1, there shall be minimum monthly customer charge at the following rates even if no energy is consumed. | ||||||
a) Single Phase Connections: | Rs. 75/- per consumer per month | |||||
b) Three Phase Connections: | Rs. 150 /- per consumer per month | |||||
A-2 GENERAL SUPPLY TARIFF – COMMERCIAL | ||||||
a) | For Sanctioned load upto 5 kW | – | – | 29.34 | ||
b) | For Sanctioned load 5 kW & above | 500 | – | 31.02 | ||
– | Peak | Off-Peak | ||||
c) | Time Of Use | 500 | 32.94 | 26.97 | ||
d) | Electric Vehicle Charging Station | – | 31.02 | |||
Under tariff A-2 (a), there shall be minimum monthly charges at the following rates even if no energy is consumed. | ||||||
a) Single Phase Connections: | Rs. 175/- per consumer per month | |||||
b) Three Phase Connections: | Rs. 350 /- per consumer per month | |||||
Fix Charges shall be billed based on 50% off sactioned load or actual MDI for the Month which ever is higher.In such case there would be no minimum monthly charges even if no energy is consumed. | ||||||
A-3 GENERAL SERVICES | ||||||
a) | General Services | – | – | 28.90 | ||
Under tariff A-3, there shall be minimum monthly charges at the following rates even if no energy is consumed. | ||||||
a) Single Phase Connections: | Rs. 175/- per consumer per month | |||||
b) Three Phase Connections: | Rs. 350 /- per consumer per month | |||||
B1 | Up To 25 kW (at 400/230 Volts) | – | – | 25.92 | ||
B2(a) | Exceeding 25-500 kW (at 400 Volts) | 500 | – | 25.42 | ||
Time Of Use | Peak | Off-Peak | ||||
B1(b) | Upto 25 kW | – | 29.48 | 23.92 | ||
B2(b) | Exceeding 25-500 kW (at 400 Volts) | 500 | 29.42 | 23.71 | ||
B3 | For All Loads up to 5000 kW (at 11,33 kV) | 460 | 29.42 | 23.62 | ||
B4 | For All Loads (at 66,132 kV & above) | 440 | 29.42 | 23.52 | ||
For B1 and B1 (b) consumers there shall be a fixed minimum charge of Rs. 350 per month. | ||||||
Fixed charges shall be build based on 50% of sactioned load or actual MDI for the month which ever is higher.In such case there would be no minimum monthly charges even if no energy is consumed. | ||||||
C – SINGLE-POINT SUPPLY | ||||||
C -1 | For supply at 400/230 Volts | – | – | – | ||
a) | Sanctioned load less than 5 kW | – | – | 30.02 | ||
b) | Sanctioned load above 5 kW & up to 500 kW | 500 | – | 29.52 | ||
C -2(a) | For supply at 11,33 kV up to and including 5000 kW | 460 | – | 29.32 | ||
C -3(a) | For supply at 66 kV & above and sanctioned load above 5000 kW | 440 | – | 29.22 | ||
Time Of Use (Optional) | Peak | Off-Peak | ||||
C -1(c) | For supply at 400/230 Volts above 5 kW & up to 500 kW | 500 | 32.94 | 26.34 | ||
C -2(b) | For supply at 11,33 kV up to and including 5000 kW | 460 | 32.94 | 26.14 | ||
C -3(b) | For supply at 66 kV & above and sanctioned load above 5000 kW | 440 | 32.94 | 26.04 | ||
Fixed charges shall be build based on 50% of sactioned load or actual MDI for the month which ever is higher.In such case there would be no minimum monthly charges even if no energy is consumed. | ||||||
D – AGRICULTURE TARIFF | ||||||
D-1(a) | SCARP less than 5 kW | – | – | 26.02 | ||
D-2(a) | Agricultural Tube Wells | 200.00 | – | 15.69 | ||
– | Peak | Off-Peak | ||||
D-1(b) | SCARP 5 kW & above | 200.00 | 28.94 | 21.69 | ||
D-2(b) | Agricultural 5 kW & above | 200.00 | 15.69 | 15.69 | ||
Under this tariff, there shall be minimum monthly charges of Rs.2000/- per consumer per month, even if no energy is consumed. | ||||||
Note:- The consumers having sanctioned load less than 5 kW can opt for TOU metering. | ||||||
E – TEMPORARY SUPPLY TARIFFS | ||||||
E-1(i) | Residential Supply | – | – | 33.37 | ||
E-1(ii) | Commercial Supply | – | – | 29.73 | ||
E-2 | Industrial Supply | – | – | 27.00 | ||
For the categories of E-1(i&ii) above, the minimum bill of the consumers shall be Rs. 50/- per day subject to a minimum of Rs.500/- for the entire period of supply, even if no energy is consumed. | ||||||
F – SEASONAL INDUSTRIAL SUPPLY TARIFF | ||||||
125% of relevant industrial tariff | ||||||
Note: | Tariff-F consumers will have the option to convert to Regular Tariff and vice versa. This option can be exercised at the time of a new connection or at the beginning of the season. Once exercised , the option remains in force for at least one year. | |||||
G- PUBLIC LIGHTING | ||||||
G | Street Lighting | – | 29.02 | |||
Under Tariff G, there shall be a minimum monthly charge of Rs.500/- per month per KW of lamp capacity installed. | ||||||
H – RESIDENTIAL COLONIES ATTACHED TO INDUSTRIAL PREMISES | ||||||
H | Residential Colonies attached to industrial premises | – | – | 29.02 | ||
I – RAILWAY TRACTION | ||||||
I | Railway Traction | – | – | 29.02 | ||
This Tariff shall remain applicable for the period of 1 year from the date of notification | ||||||
Note : Financing cost surcharges @Rs. 0.43/ KWh would be applicable to all consumers (Except Life Line Consumer of the residential A-1 Category) for electricity sold. | ||||||
K – SPECIAL CONTRACTS | ||||||
1 | Azad Jammu & Kashmir (AJK) | 440 | – | 26.24 | ||
Peak | Off-Peak | |||||
Time Of Use | 440 | 31.94 | 25.04 | |||
2 | Rawat Lab | 29.02 |